PROJECT LOCATION
This project is located at various locations throughout the City. Click HERE to see project map.
PROJECT SCOPE
This project is constructing street lights and electrical services in various locations throughout the City. Locations were selected to fill in gaps within the existing system.
PROJECT SCHEDULE
Construction is planned to wrap up by the end of 2025.
PROJECT FUNDING
The funding for this project includes American Rescue Plan Act of 2021 (ARPA) funds.
PROJECT UPDATE
April 2025 - Construction is underway for all project locations (see map above). Prep work for wiring, pole installation, and getting electrical service continues. Poles will start to be installed this month. Shoulder closures and alternating one-way traffic control in the project areas can be expected to accommodate the work.
Please note that the construction will generally consist of these phases:
- Underground work (install conduit and prep for foundations)
- All locations have completed underground work. Some minor touch up work should be expected.
- Concrete (pour the concrete for the foundations and other electrical infrastructure)
- All locations have completed concrete work. Some minor clean-up work should be expected.
- Poles (install the light poles)
- Wiring (install the wiring, perform an electrical inspection, and protect the wiring from theft)
- All locations have been prepped for wiring.
- Completion (turn on and testing lights, correction of any deficiencies)
The contractor is working to be as efficient as possible, so you may see crews in your neighborhood several different times as they complete each phase of the project. Feel free to reach out if you have questions!
Week of March 31st -
- Electrical service work was completed for S 372nd Way.
- Stripping concrete forms was completed for S 373rd Street/S 372nd Way, S 364th Way, S 359th Street, and City Hall.
- No work will be performed on Thursday, April 3rd or Wednesday, April 4th.
Week of April 7th -
- Work will begin to stand poles, likely starting on 7th Way SW and on SW 314th Place.
- Work may begin to stand poles on Hoyt Road SW.
- Work to repair vandalism will be performed.
- Minor cleanup activities and prep work may be performed at all project locations.
Check back here for updates and schedule changes!
OUTREACH & COMMUNICATIONS
April 2024 - Construction Notification Postcard 한국인 (Korean) - Español (Spanish) - русский (Russian) - Tiếng Việt (Vietnamese)
PROJECT CONTACT
Kathy Davis, P.E., PTOE, RSP2I
Senior Traffic Engineer
(253) 835-2731
For additional details on this project or to find out more about other capital projects within Federal Way, click HERE to check out the City's interactive capital project map and dashboard.