Updates:

1/4/23 - The project is currently in the design phase.  Transpo Group has been contracted as the consultant 

10/10/23 - Nearing final layout design approval from WSDOT.

5/13/24 - Transpo Group is nearing 30% design submittal to the city for review.

2/27/25 - The city and WSDOT has completed review of 90% plans.

Proposed Improvements

The city has established median control throughout the length of the project to reduce the severity of collisions from driveways and side streets.  Furthermore, the city will construct a roundabout at the intersection of S 373rd Street to address the level of service failure and reduce the risk of collisions with minimal additional delay.

 

Budget

The city was awarded a Washington State Transportation Improvement Board Grant in the amount of $2,500,000 to fund this project.

Schedule

The design will occur through 2024 with construction beginning in early 2026.

Outreach

A public information meeting is scheduled for April 17th, 2025 at 6 pm.

Public Information Meeting Registration

More Information

For additional information, contact Civil Engineer, John Cole by email at John.Cole@cityoffederalway.com or by phone at 253-835-2718.

 