PROJECT LOCATION

This project is being designed and constructed in two phases.  

Phase 1:  S 288th St - Military Rd S to 34th Ave S

Phase 2: S 288th St - 16th Ave S to Military Rd S


PROJECT SCOPE

This project constructs a continuous bicycle and ADA-accessible pedestrian route along S 288th St between 16th Ave S and 34th Ave S, mid-block pedestrian crossings, and replacement of the traffic signal at Military Road.  For the most part, the existing curb and gutter, as well as existing sidewalks, will remain as-is.  This is a "road diet" project that will convert S 288th St from two vehicle lanes in each direction, to a single lane in each direction along with a two-way-left-turn lane and bicycle lanes. 

 Additional information on road diets can be found HERE.  


PROJECT SCHEDULE

Phase 1: Construction started during the 2023 construction season & completed during 2024.  ICON Materials is the contractor.

Phase 2:  Construction is planned to begin in spring 2025 and be completed this year. Project is currently advertising for bids. 


PROJECT FUNDING

The funding for this project includes a state Transportation Improvement Board grant and also a state Bicycle and Pedestrian grant.


PROJECT UPDATES

27-Feb-2025:  

Phase 1: Construction is near completion. RRFB's have been installed but need to be adjusted for ease of access and visibility.  

Phase 2:  Project is currently advertising for bids with the bid opening for the project in early March.  Property acquisition is near complete.

26-Mar-2025

Phase 1: Project goes to LUTC for Project Acceptance on April 7, 2025.  

Phase 2:  City received 8 bids for Phase 2. Project goes to LUTC on April 7, 2025 to Award the project to the low bidder, ACI.


PROJECT CONTACT

Jonathan Strong, E.I.T.

Civil Engineer

(253)835-2753

Jonathan.Strong@federalwaywa.gov


For additional details on this project or to find out more about other capital projects within Federal Way, click HERE to check out the City's interactive capital project map and dashboard.