PROJECT LOCATION

This project is located on Military Rd S between S 320th St and SR-18.


PROJECT SCOPE

This project provides a roadway pavement overlay.  It includes ADA upgrades, asphalt planing and paving, pavement repairs, and channelization.  The project will improve driver safety; improve conditions for non-motorized users with ADA upgrades; and extend the life of the roadway surface.


PROJECT SCHEDULE

The construction contractor is ICON Materials.  Construction is planned for 2024.


PROJECT FUNDING

The funding for this project includes a federal preservation grant.


PROJECT UPDATE

11-Apr-2024: Construction started this week.  The contractor will be starting with concrete work for the ADA improvements.


PROJECT CONTACT

Jeff Huynh

Civil Engineer

(253)835-2721

Jeff.Huynh@federalwaywa.gov


For additional details on this project or to find out more about other capital projects within Federal Way, click HERE to check out the City's interactive capital project map and dashboard.