PROJECT LOCATION
This project is located on the east side of 28th Ave S between S 312th Street and S 308th Lane.
PROJECT SCOPE
This project will construct a new Joint Operations and Maintenance Facility for the City of Federal Wayβs Parks, Public Works, Community Development, and Police Departments.
PROJECT SCHEDULE
Construction August 2024 β 1st Quarter 2026
PROJECT FUNDING
Bond Proceeds: $53 Million
SWM Fund (Frontage Improvements): $1,185,000
Transportation Capital (Frontage Improvements): $2,250,000
Police Fund: $335,000
Utility and Other: $530,000
PROJECT UPDATE
7/10/24: Corpinc Construction Company is the lowest responsive, responsible bidder. City Council scheduled to award contract on July 16, 2024. Anticipate construction start the beginning of August 2024.
OUTREACH & COMMUNICATIONS
July 2024 - Construction Notification Postcard νκ΅μΈ (Korean) - EspaΓ±ol (Spanish) - ΡΡΡΡΠΊΠΈΠΉ (Russian) - TiαΊΏng Viα»t (Vietnamese)
PROJECT CONTACT
Desiree Winkler, P.E.
Public Works Deputy Director
Desiree.Winkler@federalwaywa.gov
(253) 835-2711
For additional details on this project or to find out more about other capital projects within Federal Way, click HERE to check out the City's interactive capital project map and dashboard.